Division St (CH 19) Chenoa

Section:  18-00053-00-FP

Project:  Reconstruction & Resurfacing from Boles Ave to US Rte 24

Start Date:  June 15, 2020

Status:  85% Complete

Completion Date:

Funding:  MFT (Motor Fuel Tax) & Matching

Bid Cost:  $1,327,131.00

Cost to Date:  $952,753.85

Comments:  Major work is completed.  Preparing for Aggregate Shoulders & Seeding.