Washington St, Carlock

Section:  20-00148-07-RS

Project:  Resurfacing from I-74 to US Rte 150

Start Date:  06/23/2021

Status:  100% Complete

Completion Date:  08/23/2021

Funding:  Highway

Bid Cost:  $388,278.35

Cost to Date:  $397,853.53

Comments:  Additional Incidental HMA (Hot Mix Asphalt) needed