Section: 20-00148-07-RS
Project: Resurfacing from I-74 to US Rte 150
Start Date: 06/23/2021
Status: 100% Complete
Completion Date: 08/23/2021
Funding: Highway
Bid Cost: $388,278.35
Cost to Date: $397,853.53
Comments: Additional Incidental HMA (Hot Mix Asphalt) needed